June 3, 2026

Nuvora Energy featured in Forbes: Powering the AI future

by
Reviewed by

Some big power users are not waiting for the grid at all. Shivam Tewari, who runs Nuvora Energy and advises data center and industrial clients on how to source electricity, says the thing driving the decision is the wait. “The difference in timeline between the data center or large industrial plant buildout and the regional transmission connection would, in all likelihood, be more than 5 years,” he said. Transformer shortages and jumpy capacity prices add to it, but the connection queue is the bottleneck steering clients toward building their own power on site.

Read full article here: https://www.forbes.com/sites/daraabasiita/2026/06/03/ais-power-bill-is-landing-in-a-market-most-investors-ignore/